6800 S Hwy 75 Sherman

Sherman, TX 75090 · Zone 2 Wat/Ort Cleanroom, Zone 2 Epi/Metrology + 6 more

Sherman site slated for lab, cleanroom and manufacturing renovations

Eight TDLR registrations filed from May 5 through September 18, 2026, describe renovations at this multi-tenant industrial site. Work includes lab and cleanroom remodels, a furnace retrofit, parts-cleaning space and renovations for semiconductor manufacturing. The applicant's estimated project cost is $15 million.

Summarized from Texas Department of Licensing and Regulation records · updated Sep 18, 2026

Projects
8
8 filings
Latest filing
Sep 18, 2026
since May 5, 2026
Largest scope
61,923 sf
Estimated cost
$15M
state registration

Where this project stands

Approved · construction starts Feb 15, 2027

ZONE 2 WAT/ORT CLEANROOM

6,030 sq ft · $8.0M est.

  1. RegisteredSep 18, 2026
  2. Plan review
  3. ConstructionFeb '27 – Aug '27
  4. Inspected
  5. Closed

A 6-month build is scheduled. Bids for subcontractors and suppliers usually close before the start date.

4 contacts on this project · 3 phone numbers

Permit & project history

8 projects
  1. ZONE 2 WAT/ORT CLEANROOM

    Renovation of an existing fabrication lab — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete6,030 sq ft$8.0M est.
    Tenant / owner
    Zone 2 Wat/Ort Cleanroom
    Design firm
    Pro
    Contact
    Pro
  2. Zone 2 EPI/Metrology

    Renovation of an existing lab — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete11,428 sq ft$12M est.
    Tenant / owner
    Zone 2 Epi/Metrology
    Design firm
    Pro
    Contact
    Pro
  3. Renovation of an existing storage space to be used as parts cleaning space. — coherent corp

    TDLR project registrationRenovation/AlterationProject Registered13,842 sq ft$500K est.
    Tenant / owner
    Zone 6 Parts Cleaning
    Design firm
    Pro
    Contact
    Pro
  4. Retrofit of building for furnaces — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete61,923 sq ft$10M est.
    Tenant / owner
    Zone 1 &10 Furnaces
    Design firm
    Pro
    Contact
    Pro
  5. Zone 1 &2 Wafering

    Renovation of an existing building for semiconductor manufacturing — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete13,842 sq ft$7.5M est.
    Tenant / owner
    Zone 1 &2 Wafering
    Design firm
    Pro
    Contact
    Pro
  6. ZONE 4 BAY 6

    Laboratory remodel. — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete7,501 sq ft$1.2M est.
    Tenant / owner
    Zone 4 Bay 6
    Design firm
    Pro
    Contact
    Pro
  7. ZONE 4 BAY 4

    Laboratory remodel — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete5,004 sq ft$8.0M est.
    Tenant / owner
    Zone 4 Bay 4
    Design firm
    Pro
    Contact
    Pro
  8. Test Prober

    Lab remodel — coherent corp

    TDLR project registrationRenovation/AlterationReview Complete17,846 sq ft$15M est.
    Tenant / owner
    Test Prober
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 6800 S Hwy 75 Sherman

What is being built at 6800 S Hwy 75 in Sherman?

TDLR registrations describe renovations to existing spaces at this multi-tenant industrial site, including labs, a cleanroom, furnace areas and parts-cleaning space. One registration describes renovations for semiconductor manufacturing.

Is a new semiconductor facility being built at 6800 S Hwy 75?

The records describe renovation of an existing building for semiconductor manufacturing, not construction of a new facility. That registration, TABS2026021002, was filed May 22, 2026.

What renovations are planned at the site?

The registrations cover laboratory and cleanroom work, a furnace retrofit, parts-cleaning space, wafering and a test-prober lab remodel. They were filed between May 5 and September 18, 2026.

When were the project registrations filed?

The earliest of the eight TDLR registrations was filed May 5, 2026, and the latest was filed September 18, 2026. The latest registration is TABS2027001378 for a cleanroom renovation.

What's being renovated near the Coherent Logistics Building?

TDLR records at the same address describe several renovations, including a cleanroom, laboratories, furnace areas and parts-cleaning space. The records name Coherent in the project descriptions.

What is the estimated cost of the Sherman project?

The applicant's estimated cost for the project is $15 million. This is an estimate, not a reported total project cost.