groundranger
Active · latest filing Oct 2026Commercial

12550 Timber Forest Drive

Houston, TX 77044 · Lilly Houston Campus, Lilly Houston Campus - Central Utility Building + 1 more

New lab, administration and utility buildings registered in Houston

New construction is planned at this multi-tenant campus at 12550 Timber Forest Drive, with TDLR project registrations filed from July through October 2026. The registrations cover a laboratory and administration building, a central utility building, and two shell packages for small-molecule buildings. The filings describe shell work; interior build-outs are to be submitted separately for the Lilly Houston Campus buildings.

Summarized from Texas Department of Licensing and Regulation records · updated Oct 26, 2026

Projects
4
4 filings
Latest filing
Oct 26, 2026
since Jul 16, 2026
Largest scope
181,865 sf
Estimated cost
$60M
state registration

Where this project stands

In state plan review

Lilly Houston Campus

181,865 sq ft · $60M est.

  1. RegisteredOct 26, 2026
  2. Plan reviewnow
  3. ConstructionNov '26 – Nov '28
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

4 projects
  1. Lilly Houston Campus

    Exterior shell package only. interior build out to be submitted separately. — laboratory and administration building

    TDLR project registrationNew ConstructionProject Registered181,865 sq ft$60M est.
    Tenant / owner
    Lilly Houston Campus
    Design firm
    Pro
    Contact
    Pro
  2. Exterior shell package only. interior build out to be submitted separately. — central utility building

    TDLR project registrationNew ConstructionProject Registered110,110 sq ft$45M est.
    Tenant / owner
    Lilly Houston Campus - Central Utility Building
    Design firm
    Pro
    Contact
    Pro
  3. Project Houston

    Shell building package includes building envelope, primary structural framing, and interior stairs. — small molecule utility building 22

    TDLR project registrationNew ConstructionReview Complete14,783 sq ft$9.0M est.
    Tenant / owner
    Project Houston
    Design firm
    Pro
    Contact
    Pro
  4. Project Houston

    Shell building package includes building envelope, primary structural framing, interior stairs, and elevator shafts. — small molecule headblock building 20

    TDLR project registrationNew ConstructionReview Complete56,989 sq ft$21M est.
    Tenant / owner
    Project Houston
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 12550 Timber Forest Drive

What is being built at 12550 Timber Forest Drive?

TDLR registrations list new laboratory and administration, central utility, and small-molecule utility and headblock buildings at the multi-tenant campus. The registrations were filed between July 16 and October 26, 2026.

When were projects at 12550 Timber Forest Drive registered?

The four TDLR registrations were filed July 16, September 14, and October 26, 2026.

Is a laboratory building planned at 12550 Timber Forest Drive?

Yes. A TDLR registration dated October 26, 2026, describes a new 181,865-square-foot laboratory and administration building for the Lilly Houston Campus. The registration, TABS2027004415, covers the exterior shell package.

What is the central utility building at the site?

A TDLR registration dated September 14, 2026, lists a new 110,110-square-foot central utility building for the Lilly Houston Campus. The filing, TABS2027001034, describes an exterior shell package, with interior build-out to be submitted separately.

What are Project Houston buildings 20 and 22?

TDLR registrations describe building 20 as a small-molecule headblock building and building 22 as a small-molecule utility building. Both shell packages were registered July 16, 2026, under TABS2026025406 and TABS2026025408.

Do the registrations include interior construction?

The Lilly Houston Campus filings describe exterior shell packages and state that interior build-outs will be submitted separately. The Project Houston filings describe shell work, including structural framing and interior stairs; the building 20 filing also lists elevator shafts.

How large is the laboratory and administration building?

The TDLR registration lists the laboratory and administration building at 181,865 square feet. It was registered October 26, 2026, under TABS2027004415.

Email me when plan review is complete