Structural repairs and HVAC replacement at 8509 N Capital of Texas Hwy
Permits indicate structural repairs to existing foundation, balcony and framing systems at 8509 N Capital of Texas Hwy, permitted November 12, 2026. A separate mechanical permit for replacement of the existing central heating and air system was filed June 16, 2025, and is final.
Summarized from City of Austin records · updated Nov 12, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Nov 12, 2026
- since Jun 16, 2025
- Largest scope
- —
- Listed value
- —
Where this project stands
Permit active · work underwayScope of work: 17 stack (units 1017 2017 3017) 18 stack (units 1018 2018 3018) 19 stack (units 1019 2019 3019). addition of foundation support stations to reinforce the mid-span of existing truss foundation systems. water intrusion repairs to corners of balconies where framing is compromised and truss systems for 1st-3rd floors where damaged. addition of support headers at exterior closets to accommodate relocation of bearing walls
- AppliedOct 28, 2026
- IssuedNov 12, 2026
- WorkNov '26 – May '27
- Final inspection
2 contacts on this project · 2 phone numbers
Permit & project history
2 projectsScope of work: 17 stack (units 1017 2017 3017) 18 stack (units 1018 2018 3018) 19 stack (units 1019 2019 3019). addition of foundation support stations to reinforce the mid-span of existing truss foundation systems. water intrusion repairs to corners of balconies where framing is compromised and truss systems for 1st-3rd floors where damaged. addition of support headers at exterior closets to accommodate relocation of bearing walls
Scope of work: 17 stack (units 1017 2017 3017) 18 stack (units 1018 2018 3018) 19 stack (units 1019 2019 3019). addition of foundation support stations to reinforce the mid-span of existing truss foundation systems. water intrusion repairs to corners of balconies where framing is compromised and truss systems for 1st-3rd floors where damaged. addition of support headers at exterior closets to accommodate relocation of bearing walls
City of Austin permitBuilding PermitActive- Record
- 2026-148409 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replacement of complete existing central heat and air system with or without duct work
Replacement of complete existing central heat and air system with or without duct work
City of Austin permitMechanical PermitFinal- Record
- 2025-065060 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 8509 N Capital Of Texas Hwy Nb
What work is planned at 8509 N Capital of Texas Hwy?
An active building permit calls for foundation support stations, repairs to water-damaged balcony framing and truss systems, and support headers at exterior closets. The permit was filed November 12, 2026, under permit 2026-148409 BP.
Is a new building being built at 8509 N Capital of Texas Hwy?
The records listed describe repairs to existing building systems, not construction of a new building.
What is permit 2026-148409 BP for?
The November 12, 2026, permit covers foundation support stations, repairs to damaged balcony framing and trusses on the first through third floors, and support headers at exterior closets.
Was HVAC work permitted at 8509 N Capital of Texas Hwy?
Yes. Permit 2025-065060 MP, filed June 16, 2025, covers replacement of the existing central heating and air system, with or without duct work. Its status is final.
What's being repaired near Roadvantage Suite 304?
At 8509 N Capital of Texas Hwy, about 258 meters from Roadvantage Suite 304, an active November 2026 permit covers foundation, balcony and framing repairs.
Also being built nearby
All of 78759- 8531 N Capital Of Texas Hwy NbMay 22, 2025Replacement of complete existing central heat and air system with or without duct work · 51 m away
- 8521 N Capital Of Texas Hwy NbJun 24, 2024Like for like change out of condenser and air handler with no duct work · 62 m away
- 8515 N Capital Of Texas Hwy NbMay 2, 2024Repair burnt wire in meter box need disconnect/reconnect per ae request · 103 m away
- 8535 N Capital Of Texas Hwy NbJan 5, 2026Exterior ac condenser pull out disconnect replacement. building 8535 · 106 m away
- 8539 N Capital Of Texas Hwy NbNov 12, 2026Scope of work: 77 stack (units 1077 2077 3077.) and 78 stack (units 1078 2078 3078) addition of foundation support stations to reinforce the mid-span of existing truss foundation systems. water intrusion repairs to corners of balconies where framing is compromised and truss systems for 1st-3rd floors where damaged. addition of support headers at exterior closets to accommodate relocation of bearing walls · 112 m away
- 8517 N Capital Of Texas Hwy NbNov 12, 2026Scope of work: 36 stack (units 1036 2036 3036.) addition of foundation support stations to reinforce the mid-span of existing truss foundation systems. water intrusion repairs to corners of balconies where framing is compromised and truss systems for 1st-3rd floors where damaged. addition of support headers at exterior closets to accommodate relocation of bearing walls · 113 m away
- 8527 N Capital Of Texas Hwy NbNov 6, 2026Replacement of complete existing central heat and air system with or without duct work replacement of hvac system without duct work for unit 3005 · 117 m away
- 8545 N Capital Of Texas Hwy NbSep 24, 2025Replacement of complete existing central heat and air system with or without duct work · 133 m away
- 8537 N Capital Of Texas Hwy NbNov 12, 2026Scope of work: 73 stack (units 1073 2073 3073.) addition of foundation support stations to reinforce the mid-span of existing truss foundation systems. water intrusion repairs to corners of balconies where framing is compromised and truss systems for 1st-3rd floors where damaged. addition of support headers at exterior closets to accommodate relocation of bearing walls · 139 m away
- 8551 N Capital Of Texas Hwy NbJun 1, 2026Replacement of complete existing central heat and air system with or without duct work · 148 m away
- 8553 N Capital Of Texas Hwy NbJul 22, 2025Replacement of complete existing central heat and air system with or without duct work · 158 m away
- 8523 N Capital Of Texas Hwy NbSep 24, 2025Replacement of complete existing central heat and air system with or without duct work · 159 m away