groundranger
Active · latest filing Nov 2026Residential

5008 Desert Oak Cir

Austin, TX 78749

EV charger and battery work at 5008 Desert Oak Cir

Austin permits cover electrical upgrades at 5008 Desert Oak Cir, including a Level 2 EV charger and a backup battery system with an additional meter socket. The latest permit was filed November 10, 2026; earlier permits from February and March 2025 cover slab-foundation repair.

Summarized from City of Austin records · updated Nov 10, 2026

Projects
5
5 filings
Latest filing
Nov 10, 2026
since Feb 7, 2025
Largest scope
—
Listed value
—

Where this project stands

Permit active · work underway

Install level 2 ev charger

  1. AppliedNov 6, 2026
  2. IssuedNov 10, 2026
  3. WorkNov '26 – May '27
  4. Final inspection
5% through of the permit windowNov 10, 2026 → May 9, 2027

1 contact on this project · 1 phone number

Permit & project history

5 projects
  1. Install level 2 ev charger

    Install level 2 ev charger

    City of Austin permitElectrical PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Base: installing a backup battery system and additional meter socket

    Base: installing a backup battery system and additional meter socket

    City of Austin permitElectrical PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. 200 amp service upgrade

    200 amp service upgrade

    City of Austin permitElectrical PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Express: foundation repair on a slab foundation. we intend to install 12 total press piling pier locations along the perimeter. we will improve level to the extent. revision-plumbing work

    Express: foundation repair on a slab foundation. we intend to install 12 total press piling pier locations along the perimeter. we will improve level to the extent. revision-plumbing work

    City of Austin permitPlumbing PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. Express: foundation repair on a slab foundation. we intend to install 12 total press piling pier locations along the perimeter. we will improve level to the extent

    Express: foundation repair on a slab foundation. we intend to install 12 total press piling pier locations along the perimeter. we will improve level to the extent

    City of Austin permitBuilding PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 5008 Desert Oak Cir

What is happening at 5008 Desert Oak Cir?

Austin permits document installation of a Level 2 EV charger and a backup battery system with an additional meter socket. Earlier permits cover foundation repair.

Is an EV charger being installed at 5008 Desert Oak Cir?

Yes. Austin electrical permit 2026-146891 EP, filed November 10, 2026, is for a Level 2 EV charger and is listed as active.

Is a home battery being installed at 5008 Desert Oak Cir?

An active electrical permit filed August 18, 2026, covers a backup battery system and an additional meter socket. The permit number is 2026-101816 EP.

Was foundation work permitted at 5008 Desert Oak Cir?

Yes. Building permit 2025-011745 BP, filed February 7, 2025, covers slab-foundation repair with 12 press-piling locations along the perimeter. A related plumbing permit was filed March 3, 2025.

Is a new house being built at 5008 Desert Oak Cir?

The records provided do not show a new-house permit. They document foundation repair and electrical work at the address.

Also being built nearby

All of 78749
Email me when it passes final inspection